MRTS04 earthworks: lots, layers and testing explained

How general earthworks are lotted, layered and released on Queensland TMR projects, and how to keep the lot register matching what was actually built.

Orientation

Where MRTS04 sits in the TMR specification set

Queensland's Department of Transport and Main Roads publishes earthworks requirements across a small family of documents that reference each other.

MRS04

Standard specification, general earthworks

The standard specification document for general earthworks. It is the contractual half of the pair and is read together with the technical specification.

MRTS04

Technical specification, general earthworks

The technical requirements for cut, fill, subgrade and related earthworks: materials, placement, compaction, tolerances, testing and the hold points that release the work.

MRTS03

Drainage, retaining structures and protective treatments

Covers drainage and related structures that interleave with earthworks lots on the same corridor, so lots for both often sit in one register.

MRTS05

Unbound pavements

Picks up where earthworks finishes. Pavement layers are lotted the same way, stacked on the same ground footprint as the subgrade beneath them.

This guide explains the concepts in our own words. It does not reproduce specification text, clause numbers or testing frequencies. The current issue of the specification and your project's annexures always govern, and they are published on the Transport and Main Roads specifications page.

Lotting

How a lot is defined on an earthworks job

A lot is a parcel of work of uniform material, method and conditions, built as one layer and inspected and tested as a single unit.

Uniform material and method

One source, one placement method, one set of plant and conditions. A change of borrow pit, moisture regime or compaction plant is a reason to close the lot and start another.

One layer, one lot

Each fill lift, the prepared subgrade and each capping or pavement layer is its own lot, even where they stack on the same footprint of ground.

Located by chainage and offset

Chainage from and to, left and right offsets, so the lot is unambiguous on the corridor and can be found again during an audit years later.

Reference

Earthworks layers, lot extent and release

A working summary of how earthworks layers are usually lotted and released. Treat it as orientation only, then set the detail from your specification and annexures.

Earthworks layers with the typical basis for lot extent, conformance checks and release point
LayerWhat sets the lot extentTypical conformance checksRelease
Topsoil stripStrip area, usually broken by chainage run or work frontSetout and extent, strip depth, stockpile separationWitness point before stripping starts
Cut to subgradeChainage range and offsets of uniform material and methodMaterial assessment, level and shape tolerance, proof rollHold point before capping or pavement
Fill lift / embankmentOne lift of uniform material placed under uniform conditionsSource conformance, layer thickness, density ratio, moisture ratioHold point at each lift before the next is placed
Subgrade preparationChainage range and offsets, split at material or treatment changesMoisture conditioning, compaction, proof roll, surface levelHold point before any overlying layer
Select fill / cappingChainage range and offsets per placed layerMaterial properties, thickness, density, level toleranceHold point before pavement layers

Need a starting document? Download our free earthworks ITP and lot register templates in CSV and printable PDF, no signup required.

Worked example

A subgrade lot from setout to release

The same sequence repeats hundreds of times on a corridor job, which is exactly why the register gets out of step with the ground.

1

Subgrade is prepared between chainage 1,200 and 1,400, 0 to 8 m left, all in the same material and with the same plant, so it is opened as a single lot.

2

The lot is created against the earthworks ITP, tagged to the subgrade layer, and its area is derived from the chainage extent and offsets rather than typed in by hand.

3

Moisture conditioning and compaction are completed, field density and moisture results are taken across the lot and the surface is surveyed for level and shape.

4

A proof roll is called as a hold point. The lot sits at awaiting inspection until the superintendent's representative attends.

5

Results pass, the lot is released with its conformance date, and only then does capping go over it. Had a result failed, the lot would be marked for rework and the area stays visibly blocked on the map.

In ForgeLot

Running an MRTS04-style lot register on the alignment

ForgeLot keeps the register attached to the survey geometry, so lot extents, areas and hold point status describe the actual ground.

1. Anchor lots to the design alignment

Import the design DXF, lock the control line and generate chainage. Lots are then described in the same chainage and offset language MRTS04 hold points and your ITPs already use.

2. One lot per layer, per parcel

Draw the lot by chainage range and offsets and tag its construction layer. Fill lifts, subgrade and capping over the same ground stay separate records with separate conformance.

3. Track hold points as lot status

Move each lot through awaiting inspection, awaiting testing, passed or rework required. The map recolours, so nobody covers a lot that has not been released.

4. Export the register for the superintendent

Lot numbers, chainage extents, layers, areas, statuses and conformance dates export to CSV or PDF in the structure Australian road authorities expect.

ForgeLot layer panel showing earthworks construction layers stacked on one corridorForgeLot lot panel listing lots with chainage, layer, area and ITP status
Reporting

Progress and conformance from the same records

Because status lives on the geometry, completion by layer and the conformance summary come from the records the crew already updates on site.

ForgeLot project overview showing completion by layer and lot status summary
Questions

MRTS04 and earthworks lot FAQs

Common questions from engineers and QA staff setting up lots on Queensland TMR earthworks.

More on ITPs, hold points and registers in the ITP and lot register guide.